General Design Approach

Easi-Set designers use state-of-the-art design and detailing techniques to provide the most economical and aesthetically-pleasing exterior wall system available. SlenderWall designs are in compliance with IBC, ACI, AISC, PCI Design Handbook, CRSI Manual of Standard Practice, and applicable state and local building codes. Easi-Set’s engineers consider a range of load cases when designing the wall systems including handling loads, wind, seismic, panel weight, thermal expansion as well as other applied loads specified on the contract documents.

Additionally, Easi-Set has completed numerous, independent, full-scale mock-up tests to account for wind, water, thermal and sound transmission. Various test data under the testing data tab. For additional information, please contact your Easi-Set sales representative at (540) 439-8911 or (800) 547-4045, or visit our website at

Physical Properties

The SlenderWall system is a composite, lightweight wall system that takes advantage of the unique properties of steel and concrete to achieve a durable and aesthetically-pleasing façade system. Its exterior surface is 2-inches of PVA fiber and welded wire reinforced architectural precast concrete. The panel’s interior contains 14-gauge, G90 galvanized studs on 2-foot centers. The composite section of steel studs and high-strength architectural precast concrete provide the strength and stiffness to allow the system to resist hurricane level winds and seismic movement.

Securing the 2-inch concrete facing to the steel frame are a series of proprietary, ThermaGuard stainless-steel headed fasteners. These securely connect the concrete facing to the steel frame while providing the means to allow the concrete to respond independently to thermal gradients by utilizing an air gap between the precast concrete and the stud frame. This reduces thermal transfer from the exterior to the interior of the building by as much as 25%.

The exterior 2-inch-thick architectural precast concrete face can be finished with a variety of textures, colors, shapes, applied products, or finishes. The SlenderWall precast mix utilizes 5,000 psi concrete with integral PVA fiber reinforcement and an admixture water-repellant.

physical properties 2

Panelization Options

Optimizing the precast system includes reducing the production cost and increasing the speed of erection. The examples shown in drawing details P-1 through P-4 in the Typical Details illustrate several different ways panels can be combined or split up to achieve a desired result. Depending on panel sizes, shipping limitations, erection considerations and/or connection concepts, any one of these solutions may be the one best suited for your particular project. As shown in drawing details P-2 and P-3 in the Typical Details, it is desirable to maintain a minimum section of 18-inches concrete around all openings and block-outs. Also, rough-opening-window-widths should be limited to 7-feet-0-inches unless special designs are implemented. Consult your Easi-Set sales or technical representative for assistance in providing optimal panelization options for your particular project.

In general, the economics of the design are driven by two key factors:

  • Size of panel
  • Form utilization (repetition of same form)
panelization options 1
panelization options 2

Because erection cost is typically considered on a fixed “per piece basis,” it is generally advantageous to find ways to reduce the number of erected pieces by making panels as large as possible. Note, however, that panel size is often constrained by fabrication and shipping considerations. Panel sizes can also be affected by the hauling conditions particular to the project in question and/or site conditions that may result in weight or crane reach limitations. Site access must also be considered when determining maximum panel sizes. Generally, the maximum economical size to produce is 10-feet by 35-feet. The largest panel size that can be produced is 13-feet by 40-feet, but there could be significant additional shipping costs to consider.

The second consideration in panelizing the building is form utilization, or the number of form set-ups. The more times the same form can be used, the lower the fabrication cost per piece will be. Therefore, it is extremely useful to look for ways to make maximum use of the same forms by building repetition into the shapes and sizes. This is especially important for buildings with brick finishes. Drawing Details A-9 and A-10 contained in SECTION 3.01 of this Technical Design Guide show guidelines for laying out brick patterns that reduce cost.

Your Easi-Set representative can assist you in making the most economical choices for your particular project.


SlenderWall connections are designed to allow panels to be erected as quickly as possible, thereby shortening the overall project schedule.

The most efficient connections are those that allow erectors to attach any welded-on material well before the start of erection. When possible, bolted connections can be utilized to allow the precast to be set faster as well as to allow for greater panel adjustment. Final adjustments can then be made at a later time. Coordination between the various trades must allow connections to properly interface with other building materials. Included in this Guide are a number of typical connections that provide the designer with a solid basis for cost-effective and highly-efficient designs. Consult your Easi-Set representative for your particular project to help optimize the connections and provide overall economy of materials.

Gravity connections are typically spaced at 4-feet-0-inches o.c. with tie-backs located at 6-feet-0-inches o.c. Based on actual panel size and loading conditions, these spacing guidelines may differ. This is why it is always best to involve an Easi-Set technical representative early on in the design process. This Guide also contains numerous connection concepts for various construction and/or building types. See Drawing Details S-1 through S-20 in the Typical Details.


Rotational movement of the structural support system and/or edge angles by imposed panel live and dead loads is the responsibility of the Engineer of Record to analyze for both temporary landing gravity/torsional loads and permanent gravity/torsional loads.

The Engineer of Record is also responsible for verifying the strength and stiffness of the supporting structure. Because SlenderWall panels utilize gravity supports at a 4-foot-0-inches o.c. spacing, consideration must be given to limit possible adverse effects from torsional rotation, or vertical deflection of the supporting structure. At no time should excessive torsional rotation of the supporting structure occur. The Engineer of Record must ensure that adequate bracing, stiffeners, and edge angles have been provided to allow for the optimum performance of the façade system.

Three basic types of deflection need to be considered and limited. These limitations will help ensure proper panel alignment and maintain adequate joint size. Each of these deflection limits should be noted on the Contract Documents and considered in the design of the supporting structure.

  • Deflection Type 1 – Deflection of the Supporting Structure Prior to Placement of the Panels: Prior to the placement of the precast panels, and under application of the construction dead loads, the structure will undergo a certain amount of deflection. The EOR should ensure that these deflections are within code limits. This information should also be provided to Easi-Set and coordinated with the engineer during the early design phase so that appropriate connection designs can be developed. The effects of camber should also be included in this deflection limitation.
  • Deflection Type 2 – Additional Deflection of the Supporting Structure after Erection of the Precast Panels: Once the panels are loaded onto the structure, the supporting structure could undergo an additional amount of deflection. It is extremely important to limit the amount of deflection at this critical phase as much as possible in order to allow the erector minimal need for costly posterection alignments. Therefore, it is recommended that this type of deflection be limited to 1/8-inch (preferred), with a maximum deflection of less than 1/4-inch.
  • Deflection Type 3 – Additional Long-Term Deflection of the Supporting Structure Due to the Effects of Superimposed Dead Load Plus Live Load: After the panels have been erected, the supporting structure may undergo further deflection due to the application of additional dead and live loads. These deflections should be limited to reduce the possibility of long-term degradation of the panel joints and to ensure optimal performance of the façade system.

It cannot be over-emphasized that these deflections must be noted on the Contract Documents in addition to coordinating this with Easi-Set during the design phase. Easi-Set utilizes this information in the design and detailing of the panels and their connections.

Panel Erection

Easi-Set uses a proprietary erection method – Lift-and-Release – that effectively speeds up panel installation. With the Lift-and-Release system, SlenderWall panels can be plumbed and aligned after the crane has unhooked and moved on using a turn-of-nut connection. See Drawing Details E-1 through E-4 in the Typical Details for more information on this system.

Easi-Set's choice of experienced erection companies must be PCI-qualified erectors, or have a minimum of five years experience installing SlenderWall architectural precast concrete panels. They place safety first as they set panels according to required delivery sequences and schedules. They also carefully coordinate site access and storage priorities with the general contractor to maximize the number of panels set per day, minimizing the overall erection time frame. Field crews carefully execute the connection details according to the approved engineering design.

panel erection

Joints and Reveals

The size of the joint chosen on your project should be carefully considered. Easi-Set recommends a minimum nominal joint size of ¾ -inch, to account for production and erection tolerances and to help ensure a long lasting, watertight panel joint. Joints detailed less than ¾-inch can, in some instances, result in actual panel joints smaller than caulk sub-contractors cover under warranty. It’s important to maintain a ¾ -inch joint between the precast and the window system for the very same reason. Also, it is strongly recommended that the caulk joints be inspected at regular intervals over time to ensure that degradation of the caulk has not occurred. Your Easi-Set sales team will provide specific maintenance guidelines to help assist you.

joints reveals

When selecting accent reveals or rustication lines, it’s important to tie them in to the chosen joint size. Triangular reveals are not to be used because they are difficult to affix to the forms. Instead, a trapezoidal reveal will provide a flat nailing surface for the form builders and help minimize possible nail-hole irregularities. When choosing a reveal, limit the depth to 3/8-inch. This is to maintain a minimum effective concrete thickness of 1-5/8-inches at all locations. See also Drawing Details A-1 and A-6 in the Typical Details for more information relating to joints and reveals.

Facial Projections

Facial projections can add a unique accent to your building project. Because these features are cast to the panels “bottom in form,” a minimum draft dimension is necessary in order to be able to remove the panels from after casting and curing. Without proper draft, forces generated between the concrete and the form may cause the panels to bind up during stripping and possibly damage the panel and/or forms. To ensure this does not occur, Easi-Set recommends a minimum draft of 1:6 on facial projections, as noted in the sketch below. See Drawing Details on A-7 in the Typical Details for more specific dimensional limitations. It should also be kept in mind that facial projections tend to increase production costs, since forms need to be built up to accommodate the feature.

facial projections

Panel Finishes

Architectural Brick — Second Nature Architectural Precast Concrete Brick (APCB)

Whenever possible, utilizing local aggregates and materials will help minimize cost. Your Easi-Set sales representative will help guide you through the available ranges of materials, finishes, color combinations and applied materials to help give you that one-of-a-kind look. Choosing from a sandblast finish, acid etch, exposed aggregate, thin brick, granite facing, or many other finishes will provide the unique building accent that best emulates your design intent. Available exclusively with the SlenderWall system is a proprietary finish of precast concrete architectural brick cast integrally into the panel. This finish — Second Nature Architectural Precast Concrete Brick (APCB)—is the only "Class A” precast concrete brick on the market with the level of quality necessary for "Class A” commercial projects.

Drawing Details A-9 and A-10 in the Typical Details provide excellent guidelines for maximizing form utilization and optimizing the aesthetic quality of the façade.

panel finishes

Glazing Interface

The glass, glazing, curtain-wall systems interface with the SlenderWall system in a similar fashion as with thicker traditional architectural precast concrete panel systems.  The most economical design is a flush-faced design where the window system is in alignment with the exterior face of the SlenderWall system (see Drawing A-2 in the Typical Details). This allows the window frame to overlap the 2-inch-thick SlenderWall precast. An optional upgrade allows glazing to be set back from the face of the SlenderWall precast (see Drawing A-2 in the Typical Details). A precast return is introduced to produce the desired set-back. The maximum standard return is 4-½-inches from the face of the panel. Wood blocking is then field-applied to frame around the window opening to support the glazing system.

It is important to note that the weight of the glazing system cannot bear on the precast in the SlenderWall system. All glazing loads must be transferred onto the steel-stud back-up frame. Refer to Drawing Detail A-2 in the Typical Details for details of the window head, jambs, and sill.

glazing interface

Fire Stop

In many cases the building must be designed with a fire-rated floor system. This typically means that the cavity between the edge of the floor slab and the back of precast within the SlenderWall system needs to incorporate a fire-stop or other fire safety design. This cavity is filled with a mineral-wool fireproof material. A pourable smoke seal material may or may not be used on top of the fire-stop material.

There are several UL rated assemblies utilizing proprietary fire safety material that can be used to provide the required fire safety design. Refer to Drawing Detail A-3 in the Typical Details for typical Fire Stop detail at slab edges.

Fire Rating

The standard SlenderWall system with one 5/8-inch layer of Type X drywall meets a one-hour fire rating. A two-hour rating may be achieved by adding fire-resistant materials to the back of the steel-stud frame.


Penetrations through the precast that may be required for wall hydrants, pipe penetrations and light fixtures can be cast into the panels provided the coordination for location and size is done early enough in the shop drawing development. Ideally, the location and size of these penetrations should be provided to Easi-Set designers about 8 weeks prior to fabrication. This is to ensure that the information can be incorporated into the shop drawings and fabrication drawings in adequate time. For openings less than 10-inches square, it is recommended that the penetrations be field cut. However, in no instance should the heavy-gauge stud frame be cut.

Interior Finish Applications

The SlenderWall system is designed to accept numerous types of interior finishes. These finishes can be applied directly to the heavy-gauge stud framing. When detailing the interior finish applied directly to the back of the stud frame, a note should be made in the plans and specifications indicating that there is a difference in allowable tolerances between production and installation of the SlenderWall system and the metal-stud-frame system. This means that there may be differences in the stud frame on the back of the SlenderWall panels that will need to be accommodated by the interior-finishing contractor. They should also be made aware that the standard SlenderWall frame incorporates 16-gauge vertical studs and a 14-gauge top and bottom track.

In some cases— for example, where four (4) SlenderWall panels intersect, or with a long uninterrupted exterior corridor— the designer may elect to introduce a horizontal furring strip of 5/8-inch or 1-inch. This is used to “true up” the wall system before the interior finish is applied.


The slab-edge/column-face location should be clearly defined on the Contract Documents. A 1-inch dimension is required between the edge of slab or column face and the back of the SlenderWall steel-stud back-up frame to account for tolerances both in the slab and column as well as the precast. Particular attention must be paid to slab-edge/column-face conditions along skewed or curved building edges as these areas are often the areas that cause the most difficulty during layout.

slab edge

Project Timeline

In order to optimize the SlenderWall system, it is highly recommended that Easi-Set's licensed SlenderWall producer be involved in the coordination of details, connections and panelization options early during the design development phase. Because plant availability may vary, it is best to award the SlenderWall façade contract prior to other trades. This will also facilitate incorporation of SlenderWall connections into the Contract Documents. The timeline below represents a typical project schedule, incorporating SlenderWall into the subcontract. Note that the timeline below depicts representative durations to achieve maximum economy. Depending upon project complexity, these durations may vary. Allowing for optimal lead times and production rates will help keep costs low and quality high. Easi-Set's licensed SlenderWall producer can assist you in preparing a more detailed schedule for each project to integrate into the overall project timeline.

Representative SlenderWall Project Timeline

  1. Prepare Contract Drawings
  2. Contract Awarded – 50% Contract Drawing Completed
  3. Start Shop Drawings – 3 weeks after Contract Awarded
  4. Start Production – 12 weeks after start of shop drawings
  5. Start Delivery – Duration negotiated prior to contract signing. Minimum 80% produced.

Thermal Performance

SlenderWall delivers the precast industry’s only 100% thermal-break plus air-barrier panel connection system. This proprietary connection, ThermaGuard, is a series of stainless-steel fasteners anchored to the steel stud frame that create an air gap between the precast concrete panel and the frame, reducing thermal transfer by as much as 25%.

SlenderWall also offers a plant-applied closed-cell foam continuous-insulation method which acts as an insulation, water and air barrier.

Moisture, Dew Point

SlenderWall uses a face-seal double-caulking method and offers an optional proprietary sealant joint rainscreen and leak detection system, H2Out.

h2out 1
  • 1Foam Backer Rod
  • 2Second Line of Sealant
  • 3H2Out Calibrated Drain Strip
  • 4Outer Layer of Sealant
  • 5Drain tube filled with calibrated drain strip
  • 6Leaks can be identified easily
  • 7If the first line of sealant leaks during a rain event, once the panels have dried out, the drain tube will continue to weep- creating a wet area that can be identified with binoculars from ground level.

Water Penetration: There are four forces that move water through walls—gravity, capillary action, kinetic energy and air pressure differences. Gravity will move water through an opening that slopes downward; capillary action draws water into small cracks or pores in building materials; kinetic energy refers to water leakage through walls due to the force of wind-driven droplets impinging on openings in the wall; and differences in air pressure will move water from a high pressure area to a low pressure area in search of equilibrium.

SlenderWall resists water penetration by use of the face-seal method. This is accomplished by completely sealing the exposed face. The concrete mix is designed to a higher density (minimum 5,000 psi) and incorporates an integral concrete admixture, which has proven to significantly reduce water penetration. Additionally, all joints may use a single layer or double layer—of sealant applied from the exterior. A secondary sealant joint rainscreen and leak detection system exclusive to SlenderWall is H2Out, which also can be utilized if so designed. Dow Corning and other major manufacturers have warrantied the use of their sealants in H2Out applications. (Copies of approval letters are available upon request.)

Water Vapor Penetration: Water in its gaseous state (vapor) exists in practically all air. It is expressed as the percent of humidity. The higher the air temperature and percent humidity are, the higher its density and, thus, the higher its pressure. For instance, if the outside air is 90° Fahrenheit and 75% humidity and the inside air is 75° Fahrenheit and 20% humidity, then the outside air is higher pressure than the inside air and it flows toward the lower pressure area. Designing a true pressure-equalized wall system is cumbersome and expensive. The alternative is to recognize pressure differences and construct a vapor barrier in the wall system.

In hot, humid seasons, the vapor tends to migrate from the exterior to the interior. If the climatic conditions exist where this is a concern, then a closed-cell polyurethane insulation is put on the interior side of the 2-inch concrete skin of SlenderWall. (See Material and Component Section for Dow Corning). In cold seasons, vapor tends to migrate from the interior to the exterior. In conditions where this is a concern, a layer of plastic is field-installed by others over the light-gauge steel studs on the interior before the drywall is attached.

Dew Point: A common concern when discussing vapor transmission is the dew point— that point in a wall assembly where a temperature change through the wall causes the vapor to condense. Since a vapor barrier for vapor moving in either direction can be applied with SlenderWall, the dew point is not a concern.

LEED Green Building Rating System

Green Building Rating System

The LEED Green Building Rating System is a voluntary, consensus-based program for developing high-performance sustainable buildings. Based on well-founded scientific standards, LEED emphasizes state-of-the-art strategies for sustainable site development, water savings, energy efficiency, materials selection and indoor environmental quality. It is becoming an increasingly important component of the building design.

The SlenderWall system can assist the designer in obtaining LEED Certification for the building. The number of points gained toward Certification depends upon various design factors, such as the mix used and the finish. For example, more points may be obtained if a light-colored mix is utilized, or if a Thin Brick or Architectural Precast Concrete Brick (APCB) finish is utilized. Contact an Easi-Set representative (540-439-8911 or 800-547-4045) for more specific details.

US green building council logo

Project Checklist for SlenderWall

Energy and Atmosphere

  • Minimum Energy Performance
  • Optimize Energy Performance

Materials and Resources

  • Recycled Content
  • Regional Materials

Indoor Environmental Quality

  • Minimum Acoustical Performance (LEED for Schools)
  • Enhanced Acoustical Performance (LEED for Schools)
  • Thermal Comfort - Design
  • Mold Prevention (LEED for Schools)

Innovation and Design

  • Life Cycle CO2 Reduction
  • Durability
  • Resource-Efficient Cladding System
  • LEED Accredited Professional

Beyond LEED

  • Construction Waste Management